Natural Gas Pipeline
Eskipazar-Karabük and Zonguldak-Caycuma-Bartin Natural Gas Pipeline
Client: BOTAŞ
108,3 km 16" 16,7 km 14" 45,8 km 12"
Total: 170.8 km
-
3 ea 16" Line Valve
-
1 ea 16" Take-off Valve
-
2 ea 12" Take-off Valve
-
1 ea 12" Line Valve Valve
-
1 ea 10" Take-off Valve
-
1 ea 6" Take-off Valve
-
1 ea 16" Pig Receiver Station
-
1 ea 16" Pig Launcher Station
-
1 ea 12" Pig Receiver Station
-
1 ea 40.000 m3 / h RMS A Reducing and Measuring Station
-
1 ea 60.000 m3 / h RMS A Reducing and Measuring Station
-
1 ea 10" Take-off Valve (Low Pressure)
-
2 ea 8" Take-off Valve (Low Pressure)
-
1 ea 6" Take-off Valve (Low Pressure)
-
2 ea 15.000 m3 / h MS B Measuring Station